The construction Boston's own record says is coming
A zoning approval is a public commitment to build. An approved permit awaiting fees is a start date measured in weeks. Verdwise joins every approval against every subsequent permit, so this page is not a prediction — it is a list of public records that precede construction, freshest first.
560
ZBA relief approved — no permit pulled yet
133
Article 80 Board Approved — no permit pulled yet
6,159
Permit approved, awaiting issuance (Ready to Issue / Fees)
Observed timing — counted across the decided corpus, not modeled
From zoning approval to the parcel's first permit: median 118 days (middle half: 46–321 days). 77% of parcels that build have pulled a permit within a year of approval, 90% within two.
Board-approved projects with no permit yet — a sample
| Approved | Days since | Project | Neighborhood | Units | Declared cost |
|---|---|---|---|---|---|
| 2026-07-16 | 129 | 1200 Soldiers Field Road | Allston | 58 | $20M |
| 2026-07-16 | 129 | 275 E Cottage Street | Dorchester | — | — |
| 2026-07-16 | 129 | 3326 Washington Street | Jamaica Plain | 46 | $18M |
| 2026-07-16 | 129 | 3841 Washington Street | Roslindale | 165 | $60M |
| 2026-07-16 | 129 | 4301 Washington Street | Roslindale | 16 | $8M |
| 2026-07-16 | 129 | 9 Chelsea Street | East Boston | 120 | — |
| 2026-06-18 | 157 | 172 Western Avenue | Allston | 20 | $13M |
| 2026-06-18 | 157 | 24 Mt. Everett Street | Dorchester | 16 | $4M |
| 2026-06-18 | 157 | 662-666 East Broadway | South Boston | 21 | $14M |
| 2026-06-18 | 157 | 776 Summer Street - Phase 2 | South Boston | 636 | $1.0B |
Freshest zoning approvals with no permit yet — a sample
| Decided | Days since | Address | Ward | Relief approved | Case |
|---|---|---|---|---|---|
| 2026-11-20 | 2 | 81 Sawyer AV Dorchester 02125 | 13 | Conditional Use, Parking, Height, FAR, Lot Area, Rear Setback, Side Setback, Lot Frontage | BOA1856369 |
| 2026-11-20 | 2 | 7 Helen ST Dorchester 02124 | 14 | Conditional Use, Parking, Height, FAR, Lot Area, Side Setback, Open Space | BOA1835131 |
| 2026-11-20 | 2 | 121R River ST Mattapan 02126 | 17 | Conditional Use, FAR, Lot Area, Rear Setback, Side Setback | BOA1782691 |
| 2026-11-20 | 2 | 6 Almont ST Mattapan 02126 | 18 | Conditional Use, Parking, Height | BOA1855919 |
| 2026-11-20 | 2 | 12 Snow ST Brighton 02135 | 22 | Conditional Use, Parking, FAR, Lot Area, Rear Setback, Open Space | BOA1890417 |
| 2026-11-20 | 2 | 130 Minden ST Jamaica Plain 02130 | 10 | Conditional Use, Height, Side Setback, Front Setback | BOA1870745 |
| 2026-11-20 | 2 | 31 G ST South Boston 02127 | 6 | Conditional Use, Parking, Rear Setback, Side Setback | BOA1894075 |
| 2026-11-13 | 9 | 68 Theodore Parker RD West Roxbury 02132 | 20 | Conditional Use, Height, FAR, Rear Setback, Side Setback | BOA1777438 |
| 2026-11-13 | 9 | 22 Harvard ST Charlestown 02129 | 2 | Conditional Use, Height | BOA1870900 |
| 2026-11-13 | 9 | 10 to 18 Bowdoin ST Dorchester 02124 | 14 | Conditional Use | BOA1872919 |
The full lists — and the “imminent” channel — live in the product
Inside Verdwise you can filter every signal by neighborhood, age and kind — including the thousands of permits already through review and awaiting issuance — pull each parcel's full record, and ask the assistant things like “what's coming in South Boston, and when do approved projects actually start?”
Signals are facts about public records — an approval with no subsequent permit, or a permit whose review is complete — not predictions about any owner's intent. A parcel may still never build; the observed timing above says how often, and how fast, approved parcels historically did. Sources and sync dates on data freshness.